WATER IMPROVEMENT PROJECT SCHEDULE

SCHEDULED WORK - STATELINE WATER TANK & VALLEY WOODS TANK

Division B is not yet substantially complete; it is expected to reach substantial completion within 30 – 45 days. Final completion is expected within 30 days of substantial completion.

Workers will be in and around the Water Tank's from 7:00am - 7:00pm Monday thru Friday.

SCHEDULED WORK - WATERLINE REPLACEMENT / UPGRADE

Division A is substantially complete and only punch list items remain. Final completion is expected on or before October 14th, 2026. Punch list items include but are not limited to restoration of lawn and asphalt and adjustments of curb boxes.