WATER IMPROVEMENT PROJECT SCHEDULE
December 04, 2025
WATER IMPROVEMENT PROJECT
SCHEDULED WORK - STATELINE WATER TANK
Work has started on the Stateline Water Tank.
We expect to drain the Stateline Water Tank on Monday or Tuesday 12/8/2025 or 12/9/2025. There will be running water on the ground during this process. Workers will be in and around the Stateline Water Tank from 7:00am - 7:00pm Monday thru Friday until mid-January 2026. Except on 12/24/25, 12/25/25, 12/31/25, and 1/1/26.
Tank work will NOT result in water service disruption.
SCHEDULED WORK - WATER LINES AND VALVES
CONSTRUCTION WORK HOURS ARE 7:00AM-5:30PM MONDAY THRU FRIDAY
As these valves are replaced customers in surrounding areas may experience low or no water pressure, or loss of water. The time needed to replace each valve may vary.
Removal and Installation of isolation and gate valves on the following streets in the order listed:
1898 Fieldcrest Dr -COMPLETE
1808 Fieldcrest Dr-COMPLETE
1448 Brookridge Circle Dr-COMPLETE
1622 Ridgewood Circle - COMPLETE
20711 Matterhorn Dr
20492 Matterhorn Dr
20251 Matterhorn Dr
1463 Greenlawn Way
21132 Sunnyridge Dr
21002 Sunnyridge Dr
SCHEDULED WORK - WATERLINE REPLACEMENT / UPGRADE
Water lines are being bored on Cliftmont Circle.
NO VALVE OR LINE CONSTRUCTION IS SCHEDULED ON THE FOLLOWING DATES
DECEMBER 6, 7, 12, 13, 14, 20, 21, 22, 23, 24, 25, 26, 27, 28, 31, 2025
JANUARY 1, 2026
Please Call the Office at 812-539-3330 if you have any questions or concerns.