SCHEDULED WORK FOR WATER IMPROVEMENT PROJECT
October 31, 2025
WATER IMPROVEMENT PROJECT
SCHEDULED WORK FOR THE WEEK OF
NOVEMBER 3, 2025
Installation of isolation valves on the following streets in the order listed:
Fairway Dr. – 2 valves one near 1296 and one near 1661
Par Dr. – 1 valve near 19317
Golfview Ct. - 1 valve near 1293
Kathy Ct. – 1 valve near 1463
Montclair Ct. – 2 valves one near 1217 and one near 1148
As these valves are replaced customers in surrounding areas may experience low or no water pressure, or loss of water. The time needed to replace each valve may vary.
Individual Meter Replacement
Will resume Near the Alpine Dr, Brabamhurst Dr, and Highridge Ct. area, and continue to progress clockwise around the lake.
Customers will have their water turned off as the meter is replaced, this usually takes less than 20 minutes.
Please Call the Office at 812-539-3330 if you have any questions or concerns.